For an assembly line, which statement about the feasible range of cycle time is correct?
- A. At least the total work content, so that one station can do it all
- B. At least the longest task time and at most the total work content
- C. It can be shorter than the longest task if stations work faster
- D. It must equal the takt time exactly, whatever the task times
Correct answer: B. At least the longest task time and at most the total work content
No station can cycle faster than its longest indivisible task; and a single station doing all the work needs a cycle equal to the total work content. Any cycle time between the two is feasible; takt time is the target set by demand.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A product's Q4 sales were 600 units, and its multiplicative seasonal index for Q4 is 1.25. What are its deseasonalised Q4 sales?
- Forecast errors are defined as actual − forecast. Over 12 months the mean forecast error is +35 units and the tracking signal is +5.2…
- A regression estimated with sales and advertising both in ₹ lakh is Sales = 20 + 3.5 × Ads, with R² = 0.81. If sales are re-expressed in ₹…
- A two-tailed test of whether a new checkout flow changes basket size gives p = 0.08. The team had, before seeing the data, set a…
- A 95% confidence interval for the mean delivery time is 102 to 110 minutes. At the 5% level (two-tailed), what does this imply about H0: μ…
- A call centre makes 400 outbound calls a day, and each converts independently with probability 0.1. Using the normal approximation, about…