Management & CommerceHardOps MT · MBA placement

For an assembly line, which statement about the feasible range of cycle time is correct?

  1. A. At least the total work content, so that one station can do it all
  2. B. At least the longest task time and at most the total work content
  3. C. It can be shorter than the longest task if stations work faster
  4. D. It must equal the takt time exactly, whatever the task times

Correct answer: B. At least the longest task time and at most the total work content

No station can cycle faster than its longest indivisible task; and a single station doing all the work needs a cycle equal to the total work content. Any cycle time between the two is feasible; takt time is the target set by demand.