Two paths are both critical at 15 days: A → B and A → C (A is shared). Crash costs per day: A ₹5,000, B ₹3,000, C ₹3,500, and each can be crashed by at least 1 day. What is the cheapest way to cut the project by 1 day?

  1. A. Crash B by 1 day, for ₹3,000
  2. B. Crash B and C by 1 day each, for ₹6,500
  3. C. Crash C by 1 day, for ₹3,500
  4. D. Crash A by 1 day, for ₹5,000

Correct answer: D. Crash A by 1 day, for ₹5,000

Both paths must shorten. Crashing B and C costs ₹6,500, while crashing the shared activity A shortens both paths at once for ₹5,000. Crashing B alone leaves A → C at 15 days, so the project does not shorten.