Two paths are both critical at 15 days: A → B and A → C (A is shared). Crash costs per day: A ₹5,000, B ₹3,000, C ₹3,500, and each can be crashed by at least 1 day. What is the cheapest way to cut the project by 1 day?
- A. Crash B by 1 day, for ₹3,000
- B. Crash B and C by 1 day each, for ₹6,500
- C. Crash C by 1 day, for ₹3,500
- D. Crash A by 1 day, for ₹5,000
Correct answer: D. Crash A by 1 day, for ₹5,000
Both paths must shorten. Crashing B and C costs ₹6,500, while crashing the shared activity A shortens both paths at once for ₹5,000. Crashing B alone leaves A → C at 15 days, so the project does not shorten.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- At the end of the simplex method (Big-M or Phase I), an artificial variable is still in the basis at a positive value. What does this…
- In the optimal simplex tableau of a maximisation problem, a non-basic decision variable has a reduced cost (net evaluation) of exactly…
- A transportation problem has 3 sources and 4 destinations. Written as a linear programme, how many decision variables and how many…
- Option A pays ₹100 lakh in the best case and ₹20 lakh in the worst; option B pays ₹60 lakh in the best case and ₹40 lakh in the worst…
- In a zero-sum game the row player's payoffs are R1: 3, 5, 4 and R2: 6, 2, 7 (columns C1, C2, C3). What is the value of the game?
- Base-year quantities and prices: product A 10 units at ₹5, product B 20 units at ₹2. Current prices: A ₹6, B ₹3. What is the Laspeyres…