A transportation problem has 3 sources and 4 destinations. Written as a linear programme, how many decision variables and how many supply/demand constraints does it have?

  1. A. 7 variables and 12 constraints
  2. B. 12 variables and 7 constraints
  3. C. 12 variables and 6 constraints
  4. D. 12 variables and 12 constraints

Correct answer: B. 12 variables and 7 constraints

There is one variable per route: 3 × 4 = 12. There is one constraint per source and one per destination: 3 + 4 = 7. Because the problem is balanced, one constraint is redundant, which is why a basic solution has m + n − 1 = 6 positive cells.