Management & CommerceVery hardOps MT · MBA placement
Products A and B use machines M1 and M2, each available 480 minutes a day. A needs 4 min on M1 and 2 min on M2; B needs 2 min on M1 and 5 min on M2. Which statement about daily output is correct?
- A. At 50:50 M2 limits output (~137 units); at 80:20 A:B, M1 does (~133)
- B. M1 is always the bottleneck, because A takes 4 minutes on it against 2 on M2
- C. M2 is always the bottleneck, because B takes 5 minutes on it, the longest task
- D. Both machines limit output equally at any mix, since each has 480 minutes
Correct answer: A. At 50:50 M2 limits output (~137 units); at 80:20 A:B, M1 does (~133)
At 50:50 the average load per unit is M1 3 min, M2 3.5 min, so M2 limits output to 480/3.5 ≈ 137. At 80:20 it is M1 3.6 min, M2 2.6 min, so M1 limits output to 480/3.6 ≈ 133. The bottleneck moves with the product mix.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Simple exponential smoothing is run with α = 1. What does the forecast for next period equal?
- An analyst fits a 12-variable regression to 30 months of sales and gets R² = 0.97 on that data, but forecasts for the next 6 months are…
- A process has specification width 12 mm and standard deviation 2 mm. An improvement cuts the standard deviation to 1.5 mm. What happens to…
- A process's specification limits are exactly ±3σ from the target, and it was centred. Its mean then shifts by 1σ (σ unchanged)…
- In a cost-minimising diet LP, the protein constraint (at least 50 g) is binding with a shadow price of ₹3 per gram. What happens if the…
- A feed is blended from ingredient X (30% protein) and ingredient Y (10% protein), in kg amounts x and y. The blend must be at least 20%…