Management & CommerceHardOps MT · MBA placement
A project's critical path is 120 days long, but the contract requires completion in 110 days. When CPM is computed backward from the 110-day deadline, what will activities on the critical path show?
- A. A total float of 0, as on any critical path
- B. A total float of plus 10 days
- C. A total float of minus 10 days, meaning they must be compressed by 10 days
- D. No float, because backward passes always start from the project's own length
Correct answer: C. A total float of minus 10 days, meaning they must be compressed by 10 days
If the latest finish is set to the contractual date, the backward pass gives LS < ES on the longest path: negative float of −10 days, which shows how much crashing or re-sequencing is needed.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Three activities have PERT estimates (optimistic, most likely, pessimistic) in days: P (2, 5, 14), Q (4, 6, 8), R (1, 8, 9). Which…
- An LP has the constraints x + y ≤ 10, x ≤ 6 and 2x + 2y ≤ 30, with x, y ≥ 0. Which constraint is redundant?
- Three workers must be assigned to four jobs, one job each at most, to minimise cost. How should the Hungarian method be applied?
- A firm surveys customers by first dividing them into regions and then randomly sampling within each region in proportion to its size. What…
- Across 1,000 customers, the correlation between app sessions and spend is r = 0.3, with p < 0.001. Which interpretation is correct?
- A batch of 500 components comes from a process with a 0.4% defect rate. Using the Poisson approximation, what is the probability that the…