A project's critical path is 120 days long, but the contract requires completion in 110 days. When CPM is computed backward from the 110-day deadline, what will activities on the critical path show?

  1. A. A total float of 0, as on any critical path
  2. B. A total float of plus 10 days
  3. C. A total float of minus 10 days, meaning they must be compressed by 10 days
  4. D. No float, because backward passes always start from the project's own length

Correct answer: C. A total float of minus 10 days, meaning they must be compressed by 10 days

If the latest finish is set to the contractual date, the backward pass gives LS < ES on the longest path: negative float of −10 days, which shows how much crashing or re-sequencing is needed.