Management & CommerceVery hardOps MT · MBA placement

Four jobs wait at one machine (processing days; due day): A (3; 5), B (2; 4), C (4; 12), D (5; 9). What is the maximum lateness under the earliest-due-date rule, compared with shortest processing time?

  1. A. EDD gives 5 days; SPT gives 2 days
  2. B. Both give 2 days
  3. C. EDD gives 0 days; SPT gives 5 days
  4. D. EDD gives 2 days; SPT gives 5 days

Correct answer: D. EDD gives 2 days; SPT gives 5 days

EDD order B, A, D, C finishes at 2, 5, 10, 14 – lateness −2, 0, 1, 2 – so the maximum is 2. SPT order B, A, C, D finishes D at day 14 against a due day of 9: lateness 5. EDD minimises maximum lateness on a single machine.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic