Management & CommerceVery hardOps MT · MBA placement
Four jobs wait at one machine (processing days; due day): A (3; 5), B (2; 4), C (4; 12), D (5; 9). What is the maximum lateness under the earliest-due-date rule, compared with shortest processing time?
- A. EDD gives 5 days; SPT gives 2 days
- B. Both give 2 days
- C. EDD gives 0 days; SPT gives 5 days
- D. EDD gives 2 days; SPT gives 5 days
Correct answer: D. EDD gives 2 days; SPT gives 5 days
EDD order B, A, D, C finishes at 2, 5, 10, 14 – lateness −2, 0, 1, 2 – so the maximum is 2. SPT order B, A, C, D finishes D at day 14 against a due day of 9: lateness 5. EDD minimises maximum lateness on a single machine.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A control system has three identical sensors, each with reliability 0.9, and it works if at least two of the three work (independent…
- A planner computes the EOQ using an annual demand forecast that turns out to be 50% too high (true demand is two-thirds of the forecast)…
- At a single-server counter (M/M/1) with λ = 6 per hour and μ = 8 per hour, what is the difference between the average number in the system…
- A line's tasks total 40 minutes of work per unit and the cycle time is 6 minutes. Precedence constraints force the planner to use 8…
- What does =DATE(2028,3,1) - DATE(2028,2,1) return in Excel (with the result formatted as a number)?
- Payoffs (₹ lakh) for three acts under three equally uncertain states: A: 50, 20, 10; B: 30, 30, 30; C: 70, 0, 5. Which act is chosen under…