A firm adopting Goldratt's critical chain method strips the safety margin out of each task estimate and instead places one shared buffer at the end of the project chain. What is the main reasoning?

  1. A. Task safety gets wasted (Parkinson's law, student syndrome); pooling needs less
  2. B. Buffers become unnecessary once task estimates are made accurate enough to trust
  3. C. Each task needs a larger buffer of its own to protect the deadline
  4. D. Removing buffers forces teams to crash every activity on the chain

Correct answer: A. Task safety gets wasted (Parkinson's law, student syndrome); pooling needs less

Padding hidden inside each task tends to be used up anyway (work starts late or expands to fill time). Aggregating safety into a project buffer works like risk pooling: the total protection needed is smaller than the sum of separate pads.