Management & CommerceVery hardOperations · capacity · MBA placement

A test-and-repair station takes 4 minutes per pass. 25% of units fail the test and are sent back through the same station for a full 4-minute pass, and reworked units again fail 25% of the time. What is the station's capacity in good units per hour?

  1. A. 15.00
  2. B. 12.00
  3. C. 11.25
  4. D. 20.00

Correct answer: C. 11.25

Expected passes per good unit = 1/(1 − 0.25) = 4/3, so each good unit takes 5.33 minutes: 60/5.33 = 11.25 per hour. 15 ignores rework, and 12 allows only a single rework (5 minutes).