Management & CommerceVery hardOperations · capacity · MBA placement
A test-and-repair station takes 4 minutes per pass. 25% of units fail the test and are sent back through the same station for a full 4-minute pass, and reworked units again fail 25% of the time. What is the station's capacity in good units per hour?
- A. 15.00
- B. 12.00
- C. 11.25
- D. 20.00
Correct answer: C. 11.25
Expected passes per good unit = 1/(1 − 0.25) = 4/3, so each good unit takes 5.33 minutes: 60/5.33 = 11.25 per hour. 15 ignores rework, and 12 allows only a single rework (5 minutes).
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Inspecting a part costs ₹2, and a defective part that reaches the customer costs ₹100. The process's defect rate is a stable 3%. Under…
- A sales list in A2:A101 is filtered to show only North, and the analyst has also manually hidden some North rows. Which formula sums only…
- A dashboard shows distinct active customers per month: January 3 (A, B, C), February 3 (A, B, D) and March 2 (A, E). A manager adds the…
- A hospital needs nurses in six 4-hour periods around the clock: 4, 8, 10, 7, 12 and 4 (the last period runs into the first). Each nurse…
- A distributor shipped 200 orders with 800 order lines and 20,000 units. 10 orders were incomplete; they had 16 short lines totalling 600…
- A cement company adds a new kiln only after demand has clearly exceeded current capacity for some time, accepting some lost sales to keep…