A repair shop (M/M/1) receives 10 jobs an hour. Each job in the system costs ₹200 an hour in customer waiting cost, and capacity costs ₹50 an hour for each job per hour of service rate. Treating the service rate μ as continuous, what value of μ minimises total hourly cost?

  1. A. About 11.6 jobs an hour
  2. B. About 6.3 jobs an hour
  3. C. About 20.0 jobs an hour
  4. D. About 16.3 jobs an hour

Correct answer: D. About 16.3 jobs an hour

Total cost = 50μ + 200 × λ/(μ − λ). Setting the derivative to zero gives (μ − λ)² = 200λ/50 = 40, so μ = 10 + √40 ≈ 16.3. 6.3 is just √40 (it would not even exceed λ), and 11.6 swaps the two cost rates.