Management & CommerceVery hardUGC NET Management · MBA placement (Operations)
A repair shop (M/M/1) receives 10 jobs an hour. Each job in the system costs ₹200 an hour in customer waiting cost, and capacity costs ₹50 an hour for each job per hour of service rate. Treating the service rate μ as continuous, what value of μ minimises total hourly cost?
- A. About 11.6 jobs an hour
- B. About 6.3 jobs an hour
- C. About 20.0 jobs an hour
- D. About 16.3 jobs an hour
Correct answer: D. About 16.3 jobs an hour
Total cost = 50μ + 200 × λ/(μ − λ). Setting the derivative to zero gives (μ − λ)² = 200λ/50 = 40, so μ = 10 + √40 ≈ 16.3. 6.3 is just √40 (it would not even exceed λ), and 11.6 swaps the two cost rates.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A distributor allows planned backorders. Annual demand is 12,000 units, ordering cost ₹600 an order, holding cost ₹40 a unit a year and…
- An item is ordered 500 units at a time. Lead-time demand is normal with a standard deviation of 100 units, and safety stock is 100 units…
- An item has annual demand of 10,000 units, order quantity 500 units and holding cost ₹10 a unit a year. Each stockout occasion (regardless…
- A shop orders a seasonal product once. It sells at ₹120, costs ₹70, and unsold units are cleared at ₹30. Demand is normal with mean 500…
- A warehouse keeps 60 units of safety stock for an item whose lead-time demand is normal with a standard deviation of 40 units. What cycle…
- Quarterly sales were Year 1: 40, 60, 80, 20 and Year 2: 48, 68, 88, 28. Using the ratio-to-moving-average method, what is the seasonal…