A warehouse keeps 60 units of safety stock for an item whose lead-time demand is normal with a standard deviation of 40 units. What cycle service level does this give?
- A. 93.3%
- B. 86.6%
- C. 84.1%
- D. 97.7%
Correct answer: A. 93.3%
z = 60 ÷ 40 = 1.5, and P(Z ≤ 1.5) ≈ 93.3% of cycles end without a stockout. 86.6% is the two-sided area within ±1.5σ, which is not relevant to a one-sided stockout risk.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Quarterly sales were Year 1: 40, 60, 80, 20 and Year 2: 48, 68, 88, 28. Using the ratio-to-moving-average method, what is the seasonal…
- Demand rises by exactly 10 units every period. A firm forecasts next period's demand with a simple 4-period moving average. By how many…
- For five periods of data, Σx = 15, Σy = 40, Σxy = 140 and Σx² = 55. Using the least-squares line of y on x, what is the forecast of y when…
- An np-chart monitors the number of defective forms in daily samples of 200, and the long-run defective rate is 3%. What are its 3-sigma…
- A process runs at 233 defects per million opportunities. Using the conventional 1.5-sigma long-term shift, what sigma level is this?
- A bolt's length must be 10.00 ± 0.03 mm. The process is normal with mean 10.02 mm and standard deviation 0.01 mm. About what share of…