Management & CommerceModerateMBA placement (Operations) · Bank SO

A warehouse keeps 60 units of safety stock for an item whose lead-time demand is normal with a standard deviation of 40 units. What cycle service level does this give?

  1. A. 93.3%
  2. B. 86.6%
  3. C. 84.1%
  4. D. 97.7%

Correct answer: A. 93.3%

z = 60 ÷ 40 = 1.5, and P(Z ≤ 1.5) ≈ 93.3% of cycles end without a stockout. 86.6% is the two-sided area within ±1.5σ, which is not relevant to a one-sided stockout risk.