A process runs at 233 defects per million opportunities. Using the conventional 1.5-sigma long-term shift, what sigma level is this?
- A. 3.5 sigma
- B. 4.5 sigma
- C. 6.0 sigma
- D. 5.0 sigma
Correct answer: D. 5.0 sigma
A tail area of 233 per million corresponds to z ≈ 3.5; adding the 1.5σ shift gives a sigma level of 5.0. Reporting 3.5 forgets the shift, which is also why 3.4 DPMO is called six sigma rather than 4.5.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A bolt's length must be 10.00 ± 0.03 mm. The process is normal with mean 10.02 mm and standard deviation 0.01 mm. About what share of…
- Under a Taguchi quadratic loss function, a shaft 0.5 mm off target causes a loss of ₹200. The process mean is 0.1 mm off target and its…
- A part has specification 94–106 with target 100. The process mean is 102 and the standard deviation 1.5. What is the Taguchi capability…
- A double sampling plan inspects 20 items and accepts the lot with 0 defectives, rejects it with 2 or more, and with exactly 1 defective…
- A project has two parallel paths: A (5 days) → B (6 days) and C (4 days) → D (5 days). Indirect cost is ₹5,000 a day. Crash costs per day…
- A project has a budget at completion of ₹500 lakh. At the review, planned value is ₹240 lakh, earned value ₹200 lakh and actual cost ₹250…