Management & CommerceVery hardMBA placement (Operations) · UGC NET Management

A project has two parallel paths: A (5 days) → B (6 days) and C (4 days) → D (5 days). Indirect cost is ₹5,000 a day. Crash costs per day (maximum days): A ₹2,000 (2), B ₹4,000 (2), C ₹1,500 (1), D ₹3,000 (2). What is the optimal duration and the net saving versus the normal 11 days?

  1. A. 9 days, saving ₹6,000
  2. B. 8 days, saving ₹5,500
  3. C. 11 days, as no crashing pays
  4. D. 7 days, saving ₹3,500

Correct answer: A. 9 days, saving ₹6,000

Crashing A twice (₹2,000 < ₹5,000 each day) cuts the project to 9 days, saving 2 × 3,000 = ₹6,000. Now both paths are critical, so the next day needs B + C = ₹5,500 > ₹5,000, which would reduce the saving to ₹5,500; stop at 9 days.