A project has a budget at completion of ₹500 lakh. At the review, planned value is ₹240 lakh, earned value ₹200 lakh and actual cost ₹250 lakh. If the current cost efficiency is expected to continue, what is the estimate at completion?
- A. ₹550 lakh
- B. ₹700 lakh
- C. ₹600 lakh
- D. ₹625 lakh
Correct answer: D. ₹625 lakh
CPI = 200/250 = 0.8, so EAC = BAC ÷ CPI = 500 ÷ 0.8 = ₹625 lakh. ₹550 lakh assumes the remaining work runs at budget (atypical variance), and ₹700 lakh divides the remaining work by CPI × SPI.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A machine costs ₹60,000 and has no resale value. Its running costs in years 1 to 6 are ₹10,000, ₹12,000, ₹15,000, ₹19,000, ₹24,000 and…
- Five jobs wait at one machine (processing days; due day): A (2; 3), B (4; 5), C (3; 7), D (5; 9), E (1; 10). Using Moore's (Hodgson's)…
- Directed road links (km) are: S→A 4, S→B 2, B→A 1, A→C 5, B→C 8, B→D 10, C→D 3, C→T 7, D→T 2. What is the shortest distance from S to T?
- A retailer forecasts with a 4-period moving average and orders under an order-up-to policy with a replenishment lead time of 2 periods…
- Two regional warehouses face daily demand with the same standard deviation of 40 units, and the demands have correlation 0.5. If both are…
- The first unit of a custom transformer takes 100 labour hours. Labour follows an 80% learning curve on the cumulative-average (Wright)…