Management & CommerceHardMBA placement (Operations) · UGC NET Management

A project has a budget at completion of ₹500 lakh. At the review, planned value is ₹240 lakh, earned value ₹200 lakh and actual cost ₹250 lakh. If the current cost efficiency is expected to continue, what is the estimate at completion?

  1. A. ₹550 lakh
  2. B. ₹700 lakh
  3. C. ₹600 lakh
  4. D. ₹625 lakh

Correct answer: D. ₹625 lakh

CPI = 200/250 = 0.8, so EAC = BAC ÷ CPI = 500 ÷ 0.8 = ₹625 lakh. ₹550 lakh assumes the remaining work runs at budget (atypical variance), and ₹700 lakh divides the remaining work by CPI × SPI.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic