Five jobs wait at one machine (processing days; due day): A (2; 3), B (4; 5), C (3; 7), D (5; 9), E (1; 10). Using Moore's (Hodgson's) algorithm to minimise the number of late jobs, which jobs are late?

  1. A. Only job D
  2. B. Jobs C and D
  3. C. Jobs B, C, D and E
  4. D. Jobs B and D

Correct answer: D. Jobs B and D

In EDD order, B finishes on day 6 > 5, so remove the longest job so far (B). Then D finishes on day 10 > 9, so remove the longest of A, C, D, which is D. A, C, E are on time and B, D go last: 2 late jobs, the minimum possible. Plain EDD would make 4 jobs late.