Management & CommerceVery hardMBA placement (Operations) · UGC NET Management
The first unit of a custom transformer takes 100 labour hours. Labour follows an 80% learning curve on the cumulative-average (Wright) model. How many total hours do the first 4 units take?
- A. 314 hours
- B. 256 hours
- C. 64 hours
- D. 296 hours
Correct answer: B. 256 hours
Under Wright's model the cumulative average falls 20% each time output doubles: 100 → 80 (2 units) → 64 (4 units), so 4 units take 4 × 64 = 256 hours. 314 hours applies the unit (Crawford) model, where the 4th unit alone takes 64 hours.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- In Muther's systematic layout planning, departments are rated with the closeness codes A, E, I, O, U and X. Which statement is correct?
- In TPM's 'six big losses' that feed OEE, idling and minor stoppages (a jammed sensor cleared in under a minute, many times a shift) reduce…
- A plant builds 300 units in the last week of every month and only 100 in each of the first three weeks, overloading staff at month-end. In…
- Match each quality thinker with the idea most associated with him. A. Philip Crosby B. Joseph Juran C. Kaoru Ishikawa D. Armand Feigenbaum…
- A CONWIP line releases a new job only when a finished job leaves. Its throughput is 150 jobs a day and management wants an average flow…
- A lot of 20 printed circuit boards contains exactly 3 defective boards. A buyer inspects 4 boards chosen at random without replacement…