Management & CommerceVery hardMBA placement (Operations) · UGC NET Management

The first unit of a custom transformer takes 100 labour hours. Labour follows an 80% learning curve on the cumulative-average (Wright) model. How many total hours do the first 4 units take?

  1. A. 314 hours
  2. B. 256 hours
  3. C. 64 hours
  4. D. 296 hours

Correct answer: B. 256 hours

Under Wright's model the cumulative average falls 20% each time output doubles: 100 → 80 (2 units) → 64 (4 units), so 4 units take 4 × 64 = 256 hours. 314 hours applies the unit (Crawford) model, where the 4th unit alone takes 64 hours.