A plant builds 300 units in the last week of every month and only 100 in each of the first three weeks, overloading staff at month-end. In Toyota's '3M' vocabulary, the uneven schedule itself is:

  1. A. Muda
  2. B. Mura
  3. C. Muri
  4. D. Kaizen

Correct answer: B. Mura

Muda is waste (non-value-adding activity), mura is unevenness or fluctuation, and muri is overburden of people or machines. The lumpy schedule is mura, and it causes muri at month-end; heijunka (levelling) attacks it.