Management & CommerceHardMBA placement (Operations)
A plant builds 300 units in the last week of every month and only 100 in each of the first three weeks, overloading staff at month-end. In Toyota's '3M' vocabulary, the uneven schedule itself is:
- A. Muda
- B. Mura
- C. Muri
- D. Kaizen
Correct answer: B. Mura
Muda is waste (non-value-adding activity), mura is unevenness or fluctuation, and muri is overburden of people or machines. The lumpy schedule is mura, and it causes muri at month-end; heijunka (levelling) attacks it.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Match each quality thinker with the idea most associated with him. A. Philip Crosby B. Joseph Juran C. Kaoru Ishikawa D. Armand Feigenbaum…
- A CONWIP line releases a new job only when a finished job leaves. Its throughput is 150 jobs a day and management wants an average flow…
- A lot of 20 printed circuit boards contains exactly 3 defective boards. A buyer inspects 4 boards chosen at random without replacement…
- A one-way ANOVA compares weekly sales under 3 store layouts with 10 stores each. The between-groups sum of squares is 120 and the…
- A logistic regression for loan default gives log-odds = −3 + 0.8 × (number of missed payments). For an applicant with 5 missed payments…
- A telecom churn model scores 97% accuracy on a hold-out sample, but fails in live use. Investigation shows one input was 'number of days…