In TPM's 'six big losses' that feed OEE, idling and minor stoppages (a jammed sensor cleared in under a minute, many times a shift) reduce which OEE factor?

  1. A. Availability
  2. B. Quality
  3. C. Performance
  4. D. Utilisation

Correct answer: C. Performance

Breakdowns and set-ups reduce availability; idling/minor stoppages and reduced speed reduce performance; start-up rejects and production defects reduce quality. Minor stops are usually too short to be logged as downtime, so they show up as lost speed.