Management & CommerceHardMBA placement (Operations)
In TPM's 'six big losses' that feed OEE, idling and minor stoppages (a jammed sensor cleared in under a minute, many times a shift) reduce which OEE factor?
- A. Availability
- B. Quality
- C. Performance
- D. Utilisation
Correct answer: C. Performance
Breakdowns and set-ups reduce availability; idling/minor stoppages and reduced speed reduce performance; start-up rejects and production defects reduce quality. Minor stops are usually too short to be logged as downtime, so they show up as lost speed.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A plant builds 300 units in the last week of every month and only 100 in each of the first three weeks, overloading staff at month-end. In…
- Match each quality thinker with the idea most associated with him. A. Philip Crosby B. Joseph Juran C. Kaoru Ishikawa D. Armand Feigenbaum…
- A CONWIP line releases a new job only when a finished job leaves. Its throughput is 150 jobs a day and management wants an average flow…
- A lot of 20 printed circuit boards contains exactly 3 defective boards. A buyer inspects 4 boards chosen at random without replacement…
- A one-way ANOVA compares weekly sales under 3 store layouts with 10 stores each. The between-groups sum of squares is 120 and the…
- A logistic regression for loan default gives log-odds = −3 + 0.8 × (number of missed payments). For an applicant with 5 missed payments…