Management & CommerceVery hardUGC NET Management · MBA placement (Operations)

Under a Taguchi quadratic loss function, a shaft 0.5 mm off target causes a loss of ₹200. The process mean is 0.1 mm off target and its standard deviation is 0.2 mm. What is the expected loss per shaft?

  1. A. ₹8
  2. B. ₹32
  3. C. ₹72
  4. D. ₹40

Correct answer: D. ₹40

k = 200 ÷ 0.5² = 800. Expected loss = k × (σ² + (μ − T)²) = 800 × (0.04 + 0.01) = ₹40. ₹32 counts only the variance and ₹8 only the off-centre bias.