Management & CommerceVery hardUGC NET Management

A part has specification 94–106 with target 100. The process mean is 102 and the standard deviation 1.5. What is the Taguchi capability index Cpm?

  1. A. 0.80
  2. B. 1.33
  3. C. 0.89
  4. D. 0.67

Correct answer: A. 0.80

Cpm = (USL − LSL) ÷ (6√(σ² + (μ − T)²)) = 12 ÷ (6 × √(2.25 + 4)) = 12 ÷ 15 = 0.80. Cp = 1.33 ignores the off-target mean, and Cpk = 0.89 penalises it only through the nearer limit.