An np-chart monitors the number of defective forms in daily samples of 200, and the long-run defective rate is 3%. What are its 3-sigma control limits?

  1. A. UCL ≈ 13.24, LCL ≈ −1.24
  2. B. UCL ≈ 6.72, LCL ≈ 5.28
  3. C. UCL ≈ 13.24, LCL = 0
  4. D. UCL ≈ 7.24, LCL = 0

Correct answer: C. UCL ≈ 13.24, LCL = 0

Centre = np̄ = 6 and σ = √(np̄(1 − p̄)) = √5.82 ≈ 2.41, so UCL = 6 + 7.24 ≈ 13.24. The lower limit −1.24 is negative, and a count chart cannot go below zero, so LCL is set to 0.