A shaft's diameter specification is 10.0 ± 0.6 mm. The process mean is 10.2 mm and the standard deviation is 0.15 mm. What is Cpk?
- A. 0.44
- B. 1.78
- C. 1.33
- D. 0.89
Correct answer: D. 0.89
Cp = (10.6 − 9.4) ÷ (6 × 0.15) = 1.33. Cpk = min(10.6 − 10.2, 10.2 − 9.4) ÷ (3 × 0.15) = 0.4 ÷ 0.45 = 0.89. Using the far side (0.8) gives 1.78; dividing by 6σ gives 0.44.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A part passes through three steps whose first-pass yields are 98%, 95% and 97%. What is the rolled throughput yield?
- A call centre audits 25,000 calls; each call has 5 defect opportunities, and 780 defects are found. Reference values (with the 1.5σ…
- Match each quality tool with its main use. 1. Pareto chart 2. Cause-and-effect (fishbone) diagram 3. Control chart 4. Scatter diagram a…
- Assertion (A): A process can be in statistical control and still produce many units outside specification. Reason (R): Control limits come…
- Which statements are correct? I. Poka-yoke aims to make errors impossible or immediately obvious. II. Kaizen relies mainly on large…
- A firm's annual quality costs (₹ lakh): employee quality training 4, incoming inspection 6, scrap 9, warranty claims 11, supplier…