Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
Assertion (A): A process can be in statistical control and still produce many units outside specification. Reason (R): Control limits come from the process's own variation, whereas specification limits are set by the customer or designer.
- A. Both A and R are true, and R is the correct explanation of A
- B. Both A and R are true, but R is not the correct explanation of A
- C. A is true, but R is false
- D. A is false, but R is true
Correct answer: A. Both A and R are true, and R is the correct explanation of A
Both true and R explains A: a stable but wide (or off-centre) process stays within its control limits while many units fall outside specification.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Which statements are correct? I. Poka-yoke aims to make errors impossible or immediately obvious. II. Kaizen relies mainly on large…
- A firm's annual quality costs (₹ lakh): employee quality training 4, incoming inspection 6, scrap 9, warranty claims 11, supplier…
- Using the Taguchi loss function, a deviation of 0.5 mm from target causes a loss of ₹200 per unit. What is the loss for a unit that is 0.2…
- A project's activities (duration in days; immediate predecessors): A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2…
- For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what are the total float and the free float…
- For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what is the earliest start of activity G?