Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what is the earliest start of activity G?
- A. Day 12
- B. Day 9
- C. Day 6
- D. Day 7
Correct answer: B. Day 9
G needs both D and E. EF(D) = 3 + 6 = 9; EF(E) = 4 + 2 = 6. ES(G) = max(9, 6) = 9. Taking the minimum (6) is the classic forward-pass error.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A small project has two parallel paths. Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost…
- Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1…
- A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…
- A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of…
- In an activity-on-arrow project network, a dummy activity: