For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what is the earliest start of activity G?

  1. A. Day 12
  2. B. Day 9
  3. C. Day 6
  4. D. Day 7

Correct answer: B. Day 9

G needs both D and E. EF(D) = 3 + 6 = 9; EF(E) = 4 + 2 = 6. ES(G) = max(9, 6) = 9. Taking the minimum (6) is the classic forward-pass error.