In an activity-on-arrow project network, a dummy activity:
- A. represents idle time while resources are being freed up
- B. takes the average duration of the activities it connects
- C. always lies on the critical path, since it links key events
- D. takes zero time and resources and only shows a dependency
Correct answer: D. takes zero time and resources and only shows a dependency
Dummies (dashed arrows) carry zero time and cost; they keep event numbering unique and show logical dependencies.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G…
- Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays…
- An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?
- A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate…
- In CPM, the critical path is:
- A work cell uses 200 parts per hour. A container holds 30 parts and the replenishment lead time (waiting plus processing) is 45 minutes…