In CPM, the critical path is:
- A. the longest path through the network
- B. the shortest path through the network
- C. the path with the highest total cost
- D. the path with the most activities
Correct answer: A. the longest path through the network
The project cannot finish before its longest path, so that path decides the duration and has zero float.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A work cell uses 200 parts per hour. A container holds 30 parts and the replenishment lead time (waiting plus processing) is 45 minutes…
- A dimension has specification 100 ± 6. The process standard deviation is 1.5 and its mean has drifted to 101.5. About how many parts per…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- Minimise C = 3x + 2y subject to x + y ≥ 8, x + 3y ≥ 12, 2x + y ≥ 10, x, y ≥ 0. What is the minimum value of C?