In CPM, the critical path is:

  1. A. the longest path through the network
  2. B. the shortest path through the network
  3. C. the path with the highest total cost
  4. D. the path with the most activities

Correct answer: A. the longest path through the network

The project cannot finish before its longest path, so that path decides the duration and has zero float.