Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G is delayed by 3 days, what does the project duration become?

  1. A. 21 days
  2. B. 23 days
  3. C. 19 days
  4. D. 20 days

Correct answer: A. 21 days

Critical path A–C–F–H = 20 days. G: ES = max(EF D = 9, EF E = 9) = 9, LF = 20 − 2 = 18, LS = 11 → total float 2. A 3-day delay uses the 2 days of float and pushes the end out by 1 day: 21 days. 23 assumes G is critical.