A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate probability that the whole project finishes within 32 days?

  1. A. 75%
  2. B. 73%
  3. C. 63%
  4. D. 54%

Correct answer: D. 54%

Both paths must finish. P(path 1 ≤ 32) = Φ(2/3) = 0.748; P(path 2 ≤ 32) = Φ(3/5) = 0.726. Product = 0.543 ≈ 54%. Using only the 'critical' path 1 gives 75% and overstates the chance, because path 2 has far more variance; pooling the two variances (√34) is also wrong because the paths run in parallel, not in series.