Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate probability that the whole project finishes within 32 days?
- A. 75%
- B. 73%
- C. 63%
- D. 54%
Correct answer: D. 54%
Both paths must finish. P(path 1 ≤ 32) = Φ(2/3) = 0.748; P(path 2 ≤ 32) = Φ(3/5) = 0.726. Product = 0.543 ≈ 54%. Using only the 'critical' path 1 gives 75% and overstates the chance, because path 2 has far more variance; pooling the two variances (√34) is also wrong because the paths run in parallel, not in series.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- In CPM, the critical path is:
- A work cell uses 200 parts per hour. A container holds 30 parts and the replenishment lead time (waiting plus processing) is 45 minutes…
- A dimension has specification 100 ± 6. The process standard deviation is 1.5 and its mean has drifted to 101.5. About how many parts per…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…