Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays the early start of its successors. III. When the deadline equals the critical-path length, critical activities have zero total float. IV. Total float is shared by the activities along a non-critical chain.

  1. A. II, III and IV only
  2. B. I and II only
  3. C. I, III and IV only
  4. D. I, II, III and IV

Correct answer: C. I, III and IV only

Free float is exactly the delay possible without disturbing any successor's early start, so II is false. The rest are true; using total float on one activity reduces what is left for the others on that chain.