Management & CommerceHardOps MT · Supply chain · MBA placement pattern
Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays the early start of its successors. III. When the deadline equals the critical-path length, critical activities have zero total float. IV. Total float is shared by the activities along a non-critical chain.
- A. II, III and IV only
- B. I and II only
- C. I, III and IV only
- D. I, II, III and IV
Correct answer: C. I, III and IV only
Free float is exactly the delay possible without disturbing any successor's early start, so II is false. The rest are true; using total float on one activity reduces what is left for the others on that chain.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?
- A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate…
- In CPM, the critical path is:
- A work cell uses 200 parts per hour. A container holds 30 parts and the replenishment lead time (waiting plus processing) is 45 minutes…
- A dimension has specification 100 ± 6. The process standard deviation is 1.5 and its mean has drifted to 101.5. About how many parts per…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…