An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?
- A. ₹3,200
- B. ₹3,000
- C. ₹1,200
- D. ₹2,000
Correct answer: B. ₹3,000
Cost slope = (crash cost − normal cost) ÷ (normal time − crash time) = 12,000 ÷ 4 = ₹3,000 per day. ₹3,200 divides crash cost by 10; ₹1,200 divides by 10 days.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate…
- In CPM, the critical path is:
- A work cell uses 200 parts per hour. A container holds 30 parts and the replenishment lead time (waiting plus processing) is 45 minutes…
- A dimension has specification 100 ± 6. The process standard deviation is 1.5 and its mean has drifted to 101.5. About how many parts per…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…
- A workshop makes chairs (profit ₹40 each) and tables (profit ₹70 each). A chair needs 2 carpentry hours and 3 finishing hours; a table…