An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?

  1. A. ₹3,200
  2. B. ₹3,000
  3. C. ₹1,200
  4. D. ₹2,000

Correct answer: B. ₹3,000

Cost slope = (crash cost − normal cost) ÷ (normal time − crash time) = 12,000 ÷ 4 = ₹3,000 per day. ₹3,200 divides crash cost by 10; ₹1,200 divides by 10 days.