The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a normal distribution, what is the probability (approximately) of finishing within 18 days?

  1. A. 15%
  2. B. 75%
  3. C. 85%
  4. D. 70%

Correct answer: C. 85%

te = 4 + 6 + 6 = 16 days. Variances: 0.444 + 2.778 + 0.444 = 3.667; σ = 1.915. z = (18 − 16)/1.915 = 1.04 → P ≈ 85%. Adding standard deviations instead of variances gives σ = 3 and ≈ 75%.