A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of on-time completion (z = 1.645)?
- A. 35.1 days
- B. 44.9 days
- C. 46.0 days
- D. 49.0 days
Correct answer: B. 44.9 days
Due date = 40 + 1.645 × 3 = 44.9 days. Adding the variance (9) gives 49; 35.1 is the 5% point on the wrong side.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- In an activity-on-arrow project network, a dummy activity:
- Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G…
- Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays…
- An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?
- A project has two independent paths. Path 1: expected 30 days, variance 9. Path 2: expected 29 days, variance 25. What is the approximate…
- In CPM, the critical path is: