A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of on-time completion (z = 1.645)?

  1. A. 35.1 days
  2. B. 44.9 days
  3. C. 46.0 days
  4. D. 49.0 days

Correct answer: B. 44.9 days

Due date = 40 + 1.645 × 3 = 44.9 days. Adding the variance (9) gives 49; 35.1 is the 5% point on the wrong side.