Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1 day), C ₹300 (2 days), B ₹400 (2 days), D ₹200 (1 day). Indirect (overhead) cost is ₹450 per day and the normal duration is 10 days. Which project duration minimises total cost?

  1. A. 8 days
  2. B. 7 days
  3. C. 9 days
  4. D. 10 days

Correct answer: C. 9 days

10 → 9: crash C for ₹300 and save ₹450 → worth it. 9 → 8: both paths now critical; cheapest pair is C + D = ₹500 > ₹450 → not worth it. Total costs: 10 days ₹4,500, 9 days ₹4,350, 8 days ₹4,400. Optimum = 9 days.