Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1 day), C ₹300 (2 days), B ₹400 (2 days), D ₹200 (1 day). Indirect (overhead) cost is ₹450 per day and the normal duration is 10 days. Which project duration minimises total cost?
- A. 8 days
- B. 7 days
- C. 9 days
- D. 10 days
Correct answer: C. 9 days
10 → 9: crash C for ₹300 and save ₹450 → worth it. 9 → 8: both paths now critical; cheapest pair is C + D = ₹500 > ₹450 → not worth it. Total costs: 10 days ₹4,500, 9 days ₹4,350, 8 days ₹4,400. Optimum = 9 days.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…
- A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of…
- In an activity-on-arrow project network, a dummy activity:
- Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G…
- Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays…