A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?

  1. A. 8 days; variance 4
  2. B. 8 days; variance 144
  3. C. 8 days; variance 2
  4. D. 9 days; variance 4

Correct answer: A. 8 days; variance 4

te = (a + 4m + b)/6 = (4 + 28 + 16)/6 = 8 days. σ = (b − a)/6 = 12/6 = 2, so variance = 4. A simple average (4 + 7 + 16)/3 = 9 ignores the weight on m.