A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- A. 8 days; variance 4
- B. 8 days; variance 144
- C. 8 days; variance 2
- D. 9 days; variance 4
Correct answer: A. 8 days; variance 4
te = (a + 4m + b)/6 = (4 + 28 + 16)/6 = 8 days. σ = (b − a)/6 = 12/6 = 2, so variance = 4. A simple average (4 + 7 + 16)/3 = 9 ignores the weight on m.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…
- A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of…
- In an activity-on-arrow project network, a dummy activity:
- Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G…
- Which statements about float in CPM are correct? I. Free float can never exceed total float. II. Using up an activity's free float delays…
- An activity's normal time is 10 days at a cost of ₹20,000; its crash time is 6 days at ₹32,000. What is its crash cost per day?