A small project has two parallel paths. Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1 day), C ₹300 (2 days), B ₹400 (2 days), D ₹200 (1 day). What is the minimum crashing cost to finish the project in 8 days?
- A. ₹500
- B. ₹1,000
- C. ₹600
- D. ₹800
Correct answer: D. ₹800
Normal length = 10 days (A–C); B–D = 9. Day 10 → 9: crash C (₹300); now both paths are 9. Day 9 → 8: both paths must shrink, so crash C again (₹300) and D (₹200). Total = ₹800. ₹600 crashes C twice and forgets that B–D has become critical.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1…
- A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…
- A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of…
- In an activity-on-arrow project network, a dummy activity:
- Activities (days; predecessors): A 5 (–), B 3 (–), C 8 (A), D 4 (A, B), E 6 (B), F 3 (C, D), G 7 (D, E), H 4 (F), I 2 (G). If activity G…