A small project has two parallel paths. Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1 day), C ₹300 (2 days), B ₹400 (2 days), D ₹200 (1 day). What is the minimum crashing cost to finish the project in 8 days?

  1. A. ₹500
  2. B. ₹1,000
  3. C. ₹600
  4. D. ₹800

Correct answer: D. ₹800

Normal length = 10 days (A–C); B–D = 9. Day 10 → 9: crash C (₹300); now both paths are 9. Day 9 → 8: both paths must shrink, so crash C again (₹300) and D (₹200). Total = ₹800. ₹600 crashes C twice and forgets that B–D has become critical.