For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what are the total float and the free float of activity B?

  1. A. Total float 0, free float 0
  2. B. Total float 3, free float 3
  3. C. Total float 3, free float 0
  4. D. Total float 0, free float 3

Correct answer: C. Total float 3, free float 0

B: ES 0, EF 4. G's latest start = 14 − 2 − 3 = 9, so E's LF = 9, E's LS = 7 and B's LF = 7 → total float = 3. B's only successor E has ES = 4 = B's EF, so free float = 0. The float belongs to the B–E chain as a whole.