For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what are the total float and the free float of activity B?
- A. Total float 0, free float 0
- B. Total float 3, free float 3
- C. Total float 3, free float 0
- D. Total float 0, free float 3
Correct answer: C. Total float 3, free float 0
B: ES 0, EF 4. G's latest start = 14 − 2 − 3 = 9, so E's LF = 9, E's LS = 7 and B's LF = 7 → total float = 3. B's only successor E has ES = 4 = B's EF, so free float = 0. The float belongs to the B–E chain as a whole.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what is the earliest start of activity G?
- A small project has two parallel paths. Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost…
- Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1…
- A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…
- A project's critical path has an expected length of 40 days and a standard deviation of 3 days. What due date gives a 95% chance of…