A project's activities (duration in days; immediate predecessors): A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G). What is the project duration?
- A. 14 days
- B. 29 days
- C. 11 days
- D. 16 days
Correct answer: A. 14 days
Paths: A–C–F–H = 14; A–D–G–H = 14; B–E–G–H = 11. The longest path(s) give 14 days, and here there are two critical paths. 29 is the sum of all durations.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what are the total float and the free float…
- For the project A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G), what is the earliest start of activity G?
- A small project has two parallel paths. Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost…
- Path 1 is A (4 days) → C (6 days); path 2, parallel to it, is B (5 days) → D (4 days). Crash cost per day and maximum crash: A ₹500 (1…
- A PERT activity has an optimistic time of 4 days, most likely 7 days and pessimistic 16 days. What are its expected time and variance?
- The critical path of a project has three activities with PERT estimates (a, m, b) in days: (2, 4, 6), (3, 5, 13) and (4, 6, 8). Assuming a…