A project's activities (duration in days; immediate predecessors): A 3 (–), B 4 (–), C 5 (A), D 6 (A), E 2 (B), F 4 (C), G 3 (D, E), H 2 (F, G). What is the project duration?

  1. A. 14 days
  2. B. 29 days
  3. C. 11 days
  4. D. 16 days

Correct answer: A. 14 days

Paths: A–C–F–H = 14; A–D–G–H = 14; B–E–G–H = 11. The longest path(s) give 14 days, and here there are two critical paths. 29 is the sum of all durations.