The number of defective items in a batch follows a binomial distribution with mean 4 and variance 3. What are n and p?
- A. n = 12, p = 1/3
- B. n = 16, p = 0.75
- C. n = 8, p = 0.5
- D. n = 16, p = 0.25
Correct answer: D. n = 16, p = 0.25
np = 4 and np(1 − p) = 3, so 1 − p = 0.75, p = 0.25 and n = 16. Choosing p = 0.75 confuses p with q.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Delivery times are normal with mean 35 minutes and standard deviation 6 minutes. The firm wants to promise a time that is met on 90% of…
- Annual spend values range from ₹20,000 to ₹1,20,000, with mean ₹50,000 and standard deviation ₹8,000. For a customer spending ₹70,000…
- A new customer has (spend score, visits) = (5, 5). Labelled customers are P1 (4, 5) Buy, P2 (6, 6) No, P3 (5, 7) Buy, P4 (8, 5) No, P5 (5…
- One-dimensional k-means is run on the values 2, 4, 10, 12, 20 with starting centroids 3 and 15. After one assignment-and-update step, what…
- A plant uses the run-out-time method to choose its next production run. Items (stock; weekly demand): A (300; 50), B (200; 40), C (120…
- Order values have mean ₹520, median ₹480 and standard deviation ₹80. What is Pearson's second coefficient of skewness?