An assembly line with a cycle time of 10 minutes has four stations with loads of 9, 10, 8 and 7 minutes. What is its smoothness index?

  1. A. 3.74
  2. B. 2.45
  3. C. 6.00
  4. D. 14.00

Correct answer: A. 3.74

Smoothness index = √Σ(Smax − Si)² = √(1² + 0² + 2² + 3²) = √14 ≈ 3.74, where Smax = 10 is the largest station time. 14 forgets the square root and 6 sums idle times without squaring; a perfectly balanced line scores 0.