Management & CommerceHardUGC NET Management
An assembly line with a cycle time of 10 minutes has four stations with loads of 9, 10, 8 and 7 minutes. What is its smoothness index?
- A. 3.74
- B. 2.45
- C. 6.00
- D. 14.00
Correct answer: A. 3.74
Smoothness index = √Σ(Smax − Si)² = √(1² + 0² + 2² + 3²) = √14 ≈ 3.74, where Smax = 10 is the largest station time. 14 forgets the square root and 6 sums idle times without squaring; a perfectly balanced line scores 0.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A pilot work-sampling study suggests machines are idle 20% of the time. How many random observations are needed to estimate the idle share…
- A time study records an average observed time of 2.0 minutes for an element, the operator is rated at 110%, and allowances are 15% of…
- Daily demand for a spare part is 0, 1, 2 or 3 units with probabilities 0.1, 0.3, 0.4 and 0.2. What are the mean and variance of daily…
- Urgent IT tickets arrive at an average of 3 an hour (Poisson). What is the probability that more than 2 tickets arrive in a 30-minute…
- Service times at a counter are exponential with a mean of 4 minutes. What is the probability that a service takes more than 8 minutes?
- A churn model outputs probabilities, and the team flags customers above a cut-off of 0.5. If it raises the cut-off to 0.8, what usually…