Management & CommerceHardMBA Placement · Project Analyst
A project has two independent paths that both end the project: A (6 days) then C (5 days), and B (8 days) then D (2 days). Crash costs and limits: A ₹400/day (max 2 days), C ₹250/day (max 1 day), B ₹300/day (max 2 days), D ₹150/day (max 1 day). What is the minimum crashing cost to finish in 9 days?
- A. ₹800
- B. ₹650
- C. ₹500
- D. ₹950
Correct answer: A. ₹800
Path A–C (11) needs 2 days: C once (₹250) then A once (₹400). Path B–D (10) needs 1 day: D (₹150). Total ₹800. ₹650 forgets that B–D also exceeds 9 days; ₹500 crashes C twice beyond its limit; ₹950 crashes B instead of D.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm moves 36,500 units a year of a ₹2,000 part. Sea freight takes 6 days in transit; air takes 1 day. The buyer owns goods in transit…
- A warehouse ships SKU P at 300 units/day and holds on average 1,200 units of it; SKU Q ships 100 units/day with 1,000 units on hand on…
- A single-server M/M/1 counter has utilisation 0.8. Demand grows so utilisation becomes 0.9 with the same service rate. By what factor does…
- An item has 50 units on hand at the start of week 1. The master schedule has receipts of 100 in week 1 and 100 in week 3. Customer orders…
- Net requirements for four weeks are 60, 40, 100 and 30 units. Setup cost is ₹150 per order and holding cost ₹1.5 per unit per week…
- A buyer samples 50 units from each lot and accepts the lot if at most 2 are defective. If a lot is exactly 2% defective, what is the…