A project has two independent paths that both end the project: A (6 days) then C (5 days), and B (8 days) then D (2 days). Crash costs and limits: A ₹400/day (max 2 days), C ₹250/day (max 1 day), B ₹300/day (max 2 days), D ₹150/day (max 1 day). What is the minimum crashing cost to finish in 9 days?

  1. A. ₹800
  2. B. ₹650
  3. C. ₹500
  4. D. ₹950

Correct answer: A. ₹800

Path A–C (11) needs 2 days: C once (₹250) then A once (₹400). Path B–D (10) needs 1 day: D (₹150). Total ₹800. ₹650 forgets that B–D also exceeds 9 days; ₹500 crashes C twice beyond its limit; ₹950 crashes B instead of D.