An item has 50 units on hand at the start of week 1. The master schedule has receipts of 100 in week 1 and 100 in week 3. Customer orders already booked are 70 (week 1), 40 (week 2), 60 (week 3) and 30 (week 4). Using discrete available-to-promise, how many units can still be promised for delivery in week 1?

  1. A. 40
  2. B. 80
  3. C. 10
  4. D. 50

Correct answer: A. 40

Week-1 ATP = on-hand + week-1 MPS − booked orders until the next MPS receipt (weeks 1–2) = 50 + 100 − (70 + 40) = 40. 80 forgets that week 2's orders must also be met from this lot; 10 is the week-3 ATP (100 − 60 − 30).