Three sales managers must each take one of four territories (one territory stays unassigned). Monthly profit (₹ lakh): S1 – T1 40, T2 32, T3 26, T4 30; S2 – T1 36, T2 30, T3 22, T4 34; S3 – T1 44, T2 28, T3 24, T4 32. What is the maximum total profit?
- A. ₹120 lakh
- B. ₹110 lakh
- C. ₹104 lakh
- D. ₹102 lakh
Correct answer: B. ₹110 lakh
Add a dummy manager row of zeros and maximise (or minimise regrets): S1–T2 (32), S2–T4 (34), S3–T1 (44) = 110. Taking each row's best in turn gives 40 + 34 + 28 = 102; 120 sums the row maxima and gives T1 to two people.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A campus must link five buildings with fibre at least total length. Possible links (metres ×10): P–Q 7, P–R 5, Q–R 4, Q–S 6, R–S 9, R–T 8…
- A truck can carry 10 tonnes. Consignments (weight; profit): A (6 t; ₹36 lakh), B (5 t; ₹28 lakh), C (5 t; ₹27 lakh), D (3 t; ₹15 lakh)…
- In a zero-sum game, player A's payoffs are: A plays R1 – 4 against B's C1 and −2 against C2; A plays R2 – −1 against C1 and 3 against C2…
- A SKU is reordered 20 times a year. Management accepts at most one stockout every two years. Demand during lead time is normal with σ = 50…
- For a raw material: weekly usage is minimum 200, normal 300 and maximum 400 units; lead time is 4–6 weeks (normal 5); reorder quantity is…
- Weekly demand is 1,000 units (σ = 100 units a week, 52 weeks). Domestic supplier A: price ₹500, freight ₹10/unit, lead time 1 week…