A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total and 16 of them are defective. The OEE is closest to
- A. 98.0%
- B. 83.8%
- C. 81.7%
- D. 90.0%
Correct answer: C. 81.7%
Availability = 432/480 = 90%, performance = (0.5 × 800)/432 = 92.6%, quality = 784/800 = 98%. OEE = 0.9 × 0.926 × 0.98 = 81.7% (equivalently 392/480). The 83.8% would assume a 95% performance rate.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to
- A p-chart monitors a process with an average fraction defective of 0.04 using samples of 200. The 3-sigma control limits are
- A service centre has on average 12 customers in the system (waiting plus being served), customers arrive at 4 per minute and the average…
- Prior probabilities of two market states are 0.4 and 0.6. Payoffs: Alternative A gives 100 and 20; B gives 60 and 60; C gives 10 and 150…
- The bullwhip effect lower bound for demand amplification with a lead time L = 2 periods and order-up-to forecasting by a simple moving…
- A firm has sales ₹3,650, COGS ₹2,190, inventory ₹450, receivables ₹450 and payables ₹180 (a 365-day year, closing balances). The cash…