A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total and 16 of them are defective. The OEE is closest to

  1. A. 98.0%
  2. B. 83.8%
  3. C. 81.7%
  4. D. 90.0%

Correct answer: C. 81.7%

Availability = 432/480 = 90%, performance = (0.5 × 800)/432 = 92.6%, quality = 784/800 = 98%. OEE = 0.9 × 0.926 × 0.98 = 81.7% (equivalently 392/480). The 83.8% would assume a 95% performance rate.