A line works 8 hours with a 30-minute break and must make 300 units. The takt time is
- A. 1.5 minutes
- B. 1.6 minutes
- C. 0.67 minutes
- D. 2.0 minutes
Correct answer: A. 1.5 minutes
Available time = 480 − 30 = 450 minutes. Takt = 450/300 = 1.5 minutes per unit. Ignoring the break gives 1.6.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Daily demand averages 100 units with a standard deviation of 20. The lead time is a fixed 9 days and the service level requires z = 1.65…
- A warehouse has 240 orders in process on average and ships 30 orders an hour. By Little's law, the average time an order spends in the…
- Monthly demand in the last four months was 120, 135, 150 and 141. The three-month simple moving average forecast for next month is
- Task times on an assembly line add up to 54 minutes, with a cycle time of 9 minutes. If the line is balanced onto 7 stations, the balance…
- A machine has an availability of 90%, a performance rate of 95% and a quality rate of 98%. Its overall equipment effectiveness (OEE) is
- A regression of weekly demand on week number for weeks 1 to 5 uses demand values of 12, 15, 19, 22 and 27. The forecast for week 6 is