The first unit of a job takes 100 hours and the cumulative average time follows an 80% learning curve. Total hours for units 5 to 8 together are

  1. A. 204.8
  2. B. 153.6
  3. C. 128
  4. D. 102.4

Correct answer: B. 153.6

Cumulative average for 4 units = 100 × 0.8² = 64, so total = 256. For 8 units, average = 51.2 and total = 409.6. Units 5–8 take 409.6 − 256 = 153.6 hours.