Management & CommerceVery hardNMAT · SNAP
The first unit of a job takes 100 hours and the cumulative average time follows an 80% learning curve. Total hours for units 5 to 8 together are
- A. 204.8
- B. 153.6
- C. 128
- D. 102.4
Correct answer: B. 153.6
Cumulative average for 4 units = 100 × 0.8² = 64, so total = 256. For 8 units, average = 51.2 and total = 409.6. Units 5–8 take 409.6 − 256 = 153.6 hours.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A regression with n = 30 observations and k = 4 predictors has R² = 0.80. The adjusted R² is
- A service has two servers, each serving 20 customers an hour (M/M/2), and arrivals of 30 an hour. The average number of customers waiting…
- A project has two activities in sequence on the critical path: A takes 8 days (can be cut by 3 days at ₹400 a day) and B takes 6 days (can…
- Machine A makes 60% of items with a 2% defect rate; machine B makes 40% with a 5% defect rate. An item chosen at random is defective. The…
- Two warehouses each face independent weekly demand with a standard deviation of 30 and the same lead time and service level. If they are…
- A bottling unit has a design capacity of 500 crates per day and an effective capacity of 400 crates per day. Last week it averaged 340…