Management & CommerceVery hardAnalyst Placement · MBA Placement
A project has two activities in sequence on the critical path: A takes 8 days (can be cut by 3 days at ₹400 a day) and B takes 6 days (can be cut by 2 days at ₹300 a day). The other path is 4 days shorter than the critical path. The cheapest way to shorten the project by 3 days costs
- A. ₹900
- B. ₹1,200
- C. ₹1,000
- D. ₹1,100
Correct answer: C. ₹1,000
Crash the cheaper activity B fully: 2 days × 300 = 600, then A for 1 day = 400. Total = ₹1,000. The other path has 4 days of slack, so it does not become critical.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Machine A makes 60% of items with a 2% defect rate; machine B makes 40% with a 5% defect rate. An item chosen at random is defective. The…
- Two warehouses each face independent weekly demand with a standard deviation of 30 and the same lead time and service level. If they are…
- A bottling unit has a design capacity of 500 crates per day and an effective capacity of 400 crates per day. Last week it averaged 340…
- Customers arrive at a pharmacy at an average rate of 40 per hour and spend an average of 15 minutes inside. On average, how many customers…
- A plant runs one 7.5-hour shift with 30 minutes of breaks. Daily customer demand is 840 units. What is the takt time?
- A three-stage process: Stage 1 has one machine taking 6 min per unit; Stage 2 has two identical machines in parallel, each taking 15 min…