A project has two activities in sequence on the critical path: A takes 8 days (can be cut by 3 days at ₹400 a day) and B takes 6 days (can be cut by 2 days at ₹300 a day). The other path is 4 days shorter than the critical path. The cheapest way to shorten the project by 3 days costs

  1. A. ₹900
  2. B. ₹1,200
  3. C. ₹1,000
  4. D. ₹1,100

Correct answer: C. ₹1,000

Crash the cheaper activity B fully: 2 days × 300 = 600, then A for 1 day = 400. Total = ₹1,000. The other path has 4 days of slack, so it does not become critical.