Management & CommerceEasyOps MT · Supply chain · MBA placement pattern
A plant runs one 7.5-hour shift with 30 minutes of breaks. Daily customer demand is 840 units. What is the takt time?
- A. 45 seconds
- B. 30 seconds
- C. 32.1 seconds
- D. 2 minutes
Correct answer: B. 30 seconds
Available time = 450 − 30 = 420 minutes = 25,200 s. Takt = available time ÷ demand = 25,200 ÷ 840 = 30 s. Forgetting the breaks gives 27,000 ÷ 840 ≈ 32.1 s.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A three-stage process: Stage 1 has one machine taking 6 min per unit; Stage 2 has two identical machines in parallel, each taking 15 min…
- A distribution centre holds an average of 6,000 units and ships 1,200 units per week. Assuming 52 weeks a year, what is its annual…
- An assembly line must produce 1,600 units in 480 productive minutes per day. The six tasks take 10, 12, 8, 15, 7 and 9 seconds. What is…
- For the same line (work content 61 s, cycle time 18 s), precedence constraints force the planner to use 5 stations. What is the balance…
- A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average…
- A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85…