A plant runs one 7.5-hour shift with 30 minutes of breaks. Daily customer demand is 840 units. What is the takt time?

  1. A. 45 seconds
  2. B. 30 seconds
  3. C. 32.1 seconds
  4. D. 2 minutes

Correct answer: B. 30 seconds

Available time = 450 − 30 = 420 minutes = 25,200 s. Takt = available time ÷ demand = 25,200 ÷ 840 = 30 s. Forgetting the breaks gives 27,000 ÷ 840 ≈ 32.1 s.