Management & CommerceHardOps MT · Supply chain · MBA placement pattern

A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85 units/hr, yield 98%. Defective units are scrapped immediately after each stage. What is the maximum rate of good finished output?

  1. A. 85.00 units/hr
  2. B. 75.41 units/hr
  3. C. 79.38 units/hr
  4. D. 83.30 units/hr

Correct answer: C. 79.38 units/hr

Let x enter Stage 1. Stage 2 sees 0.95x ≤ 90 → x ≤ 94.74. Stage 3 sees 0.855x ≤ 85 → x ≤ 99.42. Stage 1 allows x ≤ 100. So x = 94.74 (Stage 2 binds) and good output = 90 × 0.90 × 0.98 = 79.38/hr. Applying the Stage-1 yield again to the bottleneck capacity gives 75.41.