A single-server help desk (M/M/1) receives 12 requests per hour and can serve 15 per hour. What is the average time a request waits in the queue before service starts?

  1. A. 3.2 minutes
  2. B. 16 minutes
  3. C. 20 minutes
  4. D. 4 minutes

Correct answer: B. 16 minutes

ρ = 12/15 = 0.8. Lq = ρ²/(1 − ρ) = 0.64/0.2 = 3.2. Wq = Lq/λ = 3.2/12 hr = 16 min. 20 min is W (time in system) = 1/(μ − λ); 4 min is the service time alone.