Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
A single-window ticket counter (M/M/1) has an arrival rate of 18 per hour and a service rate of 24 per hour. What is the probability that the counter is idle?
- A. 0.25
- B. 0.75
- C. 0.33
- D. 0.43
Correct answer: A. 0.25
ρ = λ/μ = 18/24 = 0.75, the probability the server is busy. P(idle) = P0 = 1 − ρ = 0.25.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Customers arrive at a single drive-through window at 20 per hour (M/M/1). Management wants the average wait in the queue (before ordering)…
- A diagnostic clinic sees 30 patients per hour. Every patient passes registration (on average 4 patients there) and a doctor (on average 6…
- A machine is available for 480 minutes a day. Product A needs 4 minutes and product B 6 minutes on it. Daily demand is 50 units of A and…
- Expected monthly demand for a service is 9,000 jobs. The firm wants a capacity cushion of 20% (measured as a share of capacity). What…
- Annual demand is 66,000 good units. Each unit needs 12 minutes of machine time. Plants run 250 days a year, 2 shifts of 8 hours, with 85%…
- A unit's design capacity is 200 units/day. Its utilisation is 75% and its efficiency is 90%. What is its effective capacity (approximately)?