Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
A machine is available for 480 minutes a day. Product A needs 4 minutes and product B 6 minutes on it. Daily demand is 50 units of A and 40 of B. What is the machine's utilisation?
- A. 91.7%
- B. 87.5%
- C. 108.3%
- D. 100.0%
Correct answer: A. 91.7%
Load = 50 × 4 + 40 × 6 = 200 + 240 = 440 min. Utilisation = 440 ÷ 480 = 91.7%.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Expected monthly demand for a service is 9,000 jobs. The firm wants a capacity cushion of 20% (measured as a share of capacity). What…
- Annual demand is 66,000 good units. Each unit needs 12 minutes of machine time. Plants run 250 days a year, 2 shifts of 8 hours, with 85%…
- A unit's design capacity is 200 units/day. Its utilisation is 75% and its efficiency is 90%. What is its effective capacity (approximately)?
- Assertion (A): Adding capacity at a non-bottleneck station does not increase the throughput of a serial process. Reason (R): The…
- Which statements about Little's law (L = λW) are correct? I. It holds in steady state whatever the arrival and service-time distributions…
- A plant works 5 days a week, 2 shifts a day. Each 8-hour shift has two 15-minute tea breaks and a 30-minute lunch. Weekly demand is 1,350…