A machine is available for 480 minutes a day. Product A needs 4 minutes and product B 6 minutes on it. Daily demand is 50 units of A and 40 of B. What is the machine's utilisation?

  1. A. 91.7%
  2. B. 87.5%
  3. C. 108.3%
  4. D. 100.0%

Correct answer: A. 91.7%

Load = 50 × 4 + 40 × 6 = 200 + 240 = 440 min. Utilisation = 440 ÷ 480 = 91.7%.